© 2024 WLRN
SOUTH FLORIDA
Play Live Radio
Next Up:
0:00
0:00
0:00 0:00
Available On Air Stations

FPL Proposes 600 Miles Of Natural Gas Pipelines

fpl.com

Hundreds of miles of proposed pipeline may begin pumping natural gas between Southwest Alabama and Martin County, Florida within four years if Florida Power and Light (FPL)gets the okay from state regulators.

This is a two-part project. The northern pipeline will stretch roughly 465 miles from Alabama to a hub in Central Florida. From there, a second line will run 126 miles to an FPL plant in Martin County. Click here to see the proposed route.

The natural gas that's piped in will be used by consumers around the state.

“This project has a central Florida hub that interconnects the existing pipeline system in Florida, the Florida Gas Transmission pipeline and the Gulfstream pipeline,” said FPL Vice President Mike Sole, “so that we also significantly improve the reliability of the pipeline infrastructure in Florida.”

Sole is the former secretary of the Florida Department of Environmental Protection.

The existing pipeline capacity is almost full, so FPL solicited proposals from companies to construct the pipelines. Two companies were chosen, and they will spend an estimated $3.6 billion to do the work.

Sole says FPL won't pay construction costs, but it will pay rent - essentially buying the right to move gas along the line.

“We hope and expect to begin construction in 2016 and complete that construction and actually begin using the pipeline in 2017,” Sole said. “We expect to see some 8,600 direct and indirect jobs associated with construction of this pipeline.”

A tentative route for each line has been established. The pipes will be buried a few feet underground, and Sole says they won't pass through much land owned by the state. The company is contacting property owners that might be impacted.

“Whether it's a transmission line, whether it's a road - when you look at Florida's geology and geography, you need to identify those corridors that already have some linear features to them like adjacent to roads or other transmission corridors,” Sole said. “That helps reduce the concerns and impacts to businesses and residents.”

FPL has to go through a lot of permitting at the federal, state and local level.

This process actually started in 2009 when the company offered up a very different proposal. The Florida Public Service Commission (PSC) rejected it and told FPL to come up with something more cost effective. That led to the current proposal.

Tom Ballinger, director of engineering for the PSC, can't comment on whether this new proposal will be approved. But he can talk about the potential impact.

Ballinger: “It's going to be a huge impact on Florida's economy. We are the second largest consumer of natural gas in the United States - Texas being the first, California actually below us.”

“It's a very highly regulated industry on the safety and the construction aspects of it. Obviously to build a large infrastructure project like this is going to take many years, many jobs,” Ballinger said. “It's going to be a huge impact on Florida's economy. We are the second largest consumer of natural gas in the United States - Texas being the first, California actually below us.”

About two-thirds of the electricity FPL supplies to Floridians is produced by natural gas.

Eric Draper, executive director of the conservation group Audubon Florida, reviewed some of the plans and evaluated the potential impact on public lands and wildlife habitat.

Draper says FPL took his advice and made a change to avoid harming a tiny federally endangered bird.

“They agreed to move the routing on the pipeline to avoid possible impacts to the Florida Grasshopper Sparrow,” Draper said.

Audubon's preferred energy source is renewable energy, but Draper says this is the next best thing. He likes the fact that if any state lands are affected by the pipelines, FPL has to pay the state one and a half times what the land is worth.

“Natural gas is going to be part of our energy future for a while. It's relatively low cost,” Draper said. “It does have some environmental cost, but we think in that case, given that we're offsetting the environmental impact of building the pipeline, this is an acceptable approach.”

The pipes could run through 16 of Florida's 67 counties.

FPL is hoping to get approval from the PSC by the end of the year.

More On This Topic